project info
A lifting station for treated water was constructed in Eskan Misr, Giza, with a capacity of 150,000 m3 per day. The scope of work on this project entailed earthwork and site mobilization, and civil and architectural works for the main pump building. Construction also included operation buildings and all assisting buildings, such as guard building, transmission building, storage building, workshops, administration building, and generator building. All required electromechanical works for the implementation of the station were also executed.
Work performed
The project capacity 150,000 m3/day -
• Earthwork and site Mobilization
• The civil and architect works for the main pump building , operation building and all assisting buildings as Guard Building , Transmission Building , storage building , workshops , administration building and generator building .
• In addition to all required electromechanical works for the implementation of the station.